Indore Development Authority Indore

The Indore Bus Rapid Transit System (BRTS) or Ahilya Path is the bus rapid transit system for the city of Indore, Madhya Pradesh by AICTSL. It became operational from 10 May 2013. The Indore BRTS project started in 2007 under the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). It involves the participation of the Governments of India and Madhya Pradesh, and the World Bank.

While the completed BRTS will cover 106 km, connecting all major corridors in Indore, Phase-I of the project proposes three corridors: the AB Road pilot corridor, the Vijayanagar Chowraha-Ujjain Road junction and Ujjain Road junction-the Airport. The current Rs. 130-crore AB Road pilot corridor runs along 11.7 km and will cater to around 70,000 passengers daily.

Construction of Pilot corridor on A.B road (Niranjanpur to rajiv Gandhi square) under bus rapid transit system indore 11.456 km (8 lane corridor) Value of work done 138.768 crores